Back to CV list
CHARLES
Personal data and contacts will be open only to employers with access to CV database
Engineering 700 000
Job Type: Full-Time , open to relocation

Education

From 0 to 2001
University of Port-Harcourt, Port-Harcourt, Rivers State
Mechanical Engineering
Languages:
English

Experience

PROJECT ENGINEER
Flobegill Nigeria Limited Client Pan Ocean Oil Corporation, Ovade- Oghara Gas Plant
September 2010 - Present Day (6 years 11 months)

• Ensured personal Health, Safety and Environment
• Involve in Site Acceptance Test ( SAT)
• Interpretation and Reviewing of all the process piping.
• Inspection of project materials to ensure that they conform to project specifications.
• Process Mechanical installation Drawings (Hook-Up Details).
• Knowledge of rotating equipment, Equipment installation details
• Provide quality management support services
• Achieved fabrication and prefabrication and all the mechanical installations all the product lines both Inspection of the weld and NDT exercises and signing off the result and its updates.
• Preparation and Supervision of hydro-test, leak test and pressure test of the storage tank.
• Provision of technical support and supervisory construction of pipeline 6’’ x 3.0km NPS schedule 80, flow line from Asaboro-4 to Asaboro -5 Satellite Manifold.
• Supervision of construction of 2ed segment single Nps 6’’ x 3.0 km schedule 80 flow-lines from boundary post to Asaboro.
• Construction of 6.8km x 6’ sch. 80 carbon steel test line from flow station to Ologbo river block valve supervision.
• Fabrication and construction of 6’’ x 3.9km sch. 80 carbon steel test line from Ologbo manifold to Ologbo River block valve.
• Provision of technical support for construction 6’’ and 4’’ pipe-line from Ogharefe-21 well head to flow-station hook-up.
• Modification Of 6’’ Flow-Line Asaboro and Manifold Hook-Up
• Provisions of technical support for construction of 6’’ x 2.5 km sch. 80 owe pipe-line to 2ed segment.
• Rehabilitation of Ologbo 2 pipeline and hook-up to Ologbo well manifold.
• Supervision of 6’’ x 10.5km sch. 80 dual flow-line, construction from Ona 2 manifold to Ona 4/5/7 manifold to well head.
• Completion of outstanding works on the 7.5km dual 6’’ & 4’’ single flow-line from ona 2 to flow station including ona 2 manifold hooks up.
• Construction of single 4’’ x 10.5 km schedule 40 Flow line at Ona 4/5/7 to Ona 2 manifold.
• Provision of technical support for construction Ossiommo Manifold header / Ligament modification.
• Supervision of Ona 7 ss, 5 ss and 4ss wellhead ligaments modification.
• Supervision of 6’’ sectional replacement of Ologbo bulk and test line.
• Modification of 6” risers of the existing flow-line from Ologbo manifold to Hook-up at flow-station.
• Rehabilitation and reinstatement of Ologbo 8 well head hook-up.
• Supervisory fabrication and installation of 6’’ schedule 80 flow-lines from Asaboro manifold to flow-station.
• Fabrication and construction 10’’ x 22km sectional replacement Jamison River.