Back to CV list
UDUAK AKPAN
Personal data and contacts will be open only to employers with access to CV database
Mechanical/piping/Electrical/Instrumentation 250 000
Job Type: Full-Time , open to relocation

Education

From 2010 to 2013
Heritage Polytechnic, City & Guilds of London institute
Mechanical Engineering, Electrical and instrumentation engineering
HND
Languages:
English Fluently

Experience

MECHANICAL & PIPING SUPERVISOR
ALCON NIG LTD [uquo Gas plant project, Eket]
July 2010 - Present Day (6 years 8 months)

 Planning and monitoring of the piping work for timely completion of the project.

 Monitoring of the pipes and inline items [fittings] bill of materials and materials receiving for installations at site.

 Assure that piping work is carried out as per P & ID'S, Layout drawing, Piping general arrangement and Line list.

 Assure that piping work is carried out as per P & ID'S, Layout drawing, Piping general arrangement and Line list.

 Supervises the installations of pipes and in-lines items [ Valves, strainers, pipes supports ]

 Monitoring the modifications of isometrics as per new revision.

 Supervision of fabrications and installations pipes, inline items and fittings.

 Check the alignment of equipments.

 Checks the insulation's lines and painting as per project specifications and standards.

 Maintain quality control and quality assurance records.

 Witness hydrostatic and radio-active testing of pipelines as per project procedures.

 Preparation of close-out reports on Piping & Mechanical completion progress.

 Attend quality and management meetings with clients for the deliberation of quality issues and work progress in line with the project schedule.

 Preparation of daily piping welding and installations report for piping production progress for timely completion of the project.

PIPING & MECHANICAL SUPERVISOR
ALCON NIG LTD
July 2010 - Present Day (6 years 8 months)

 Planning and monitoring of the piping work for timely completion of the project.

 Monitoring of the pipes and inline items [fittings] bill of materials and materials receiving for installations at site.

 Assure that piping work is carried out as per P & ID'S, Layout drawing, Piping general arrangement and Line list.

 Assure that piping work is carried out as per P & ID'S, Layout drawing, Piping general arrangement and Line list.

 Supervises the installations of pipes and in-lines items [ Valves, strainers, pipes supports ]

 Monitoring the modifications of isometrics as per new revision.

 Supervision of fabrications and installations pipes, inline items and fittings.

 Check the alignment of equipments.

 Checks the insulations lines and painting as per project specifications and standards.

 Maintain quality control and quality assurance records.

 Witness hydrostatic and radiographic testing of pipelines as per project procedures.

 Preparation of close-out reports on Piping & Mechanical completion progress.

 Attend quality and management meetings with clients for the deliberation of quality issues and work progress in line with the project schedule.

 Preparation of daily piping welding and installations report for piping production progress for timely completion of the project.